27 mines of CIL yet to start production
Coal India’s 27 mines having geological reserves of 1,200 million tonne are yet to start production.
BriefingWire.com, 12/08/2014 -
Coal India’s 27 mines having geological reserves of 1,200 million tonne are yet to start production. The reasons for the non-production of mines are stated to be delays in getting statutory clearances, land acquisition, finalisation of contract, difficult geo-mining condition and development of infrastructure facilities. At present, the coal mines are at different stages of implementation, of which five in West Bengal, three in Jharkhand, seven in Chattisgarh, four in Odisha and eight in Maharashtra. There are six projects of Coal India which are pending or yet to begin the contribution and implementation, which includes Jhanjra PSLW (R-VI) underground mine and Narainkuri underground mine. Three projects are expected to start production next fiscal, one is likely to begin in 2016-17 and another one in the year 2018-19.
|
|
|
|
|
|
|
|