When the ball mills works, motor and speed reducer transmit torque force to big and small gears of ball mill, so the barrel rotates. When the barrel rotates, Steel balls or other grinding media in the barrel are lifted to a certain height and fall down freely, so materials in the barrel are impacted. Grinding media mixing with materials impact and grind materials continuously. The grinding media and materials impact and grind each other when the ball mill rotates continuously. The final product will be discharged from outlet when it meets the request, so the grinding process is finished application range, simple structure and convenient maintenance.
If the wheel gear sounds slight beat or hoarse friction voice, and run well, you can observe continuously and find out the problems, ball mill should be stop and process; if the sound becomes louder, you should stop the machine immediately and check it.
1) during test run, the personnel should write down all kinds of records seriously.
2) Ball mill idle running. Ball mill idle running continuous operation must be more than 12~24 hours, during idle running, if problems happened, they must be solved immediately.
3) Ball mill load test run. After the ball mill had been testing normally, the load test run can be taking. Load test run should be processed in stage, feeding should be process according to the discharging situation during load test run, which can avoid the unnecessary wear and damage to steel ball and shell liner.slag mill:http://www.hx-crusher.com/n273.html
rotary sieve:http://www.hx-crusher.com/n270.html
The stages of load test run are:
(1) Add certain materials and 1/3 quantity of steel mill (max. ball load refers to ball mill instruction) test for 12~24hours.
(2) Add 2/3 quantity of steel ball run for 24~48 hours
(3) According to the discharge situation of ball mill, the output of accepted products refers to the actual ball load of the same kind beneficiation plan t to makes sure the reasonable ball load of this ball mill, then test for at least 72hours.
4) In the above process, the time of test run and increase of the load capacity should according to the big wheel gear and pinion and the running-in situation (tooth surface, temperature rise, noise, contact)of gear box. Full load test run will be process till gear surface contact precision reaches the designed requirement.
5) During test run, cooling and lubricating system of ball mill should work smooth; main bearing, transmission bearing, gear box temperature should be normal.
6) After the test run for 24~48hours of add 2/3 quantity of steel ball once again, the personnel should check and once again screw down all bolt seriously.
ball mill:http://www.hx-crusher.com/ball_mill.html